Attention to Detail and Quality Work
Pool construction came and went we finally got a pool late . Ran into some issues along the way
1) The excavation crew almost killed my trees torn up curbing and killed some shrubs .
2) Plumbing was another issue had to provide my propane because guy did not come out with some he use up the whole tank left without saying anything, He deplumed and it had to be reworked twice .
3) Either the crew who put up my wall or the crew did the deck stole my water nozzle.
4) The mason crew who installed two pillars did such a poor job they had to come out three times .
Our pool should of been done mid September but it was not. There would be days that would turn to a week for someone to show up. I understand the weather was a factor .
I had my last walk thru October 1 2013, I have some issues that need to be addressed. Nothing has been done what so ever .
I am really disappointed with the service and quality of workmanship and communication .